PROJECT INFORMATION:
|
SOLICIT # |
PROJECT NAME |
*ON-SITE WALK THROUGH DATE & TIME |
PROJECT QUESTIONS DUE BY |
RECEIVING DATE |
|
RFQ-09-08 |
Progressive Design Build Services for on Schedule Delivery of the North Lee County WTP Expansion Project |
Wednesday, July 15, 2009 @ 9:00 a.m. |
Friday, July 17, 2009 @ 5:00 p.m. |
Tuesday, July 28, 2009 @ 2:00 p.m. |
LOCATION OF MEETINGS:
*On-Site Walk Through Date & Time: Wednesday, July 15, 2009 @ 9:00 a.m., North Lee County Water Treatment Plant, 18250 Durrance Road, N Fort Myers, FL 33917 ***Please note this will be the only walk through offered for this project. No special or independent dates and/or times will be scheduled.
Receiving Date & Time: Tuesday, July 28, 2009 @ 2:00 p.m. - Community Development/Public Works, 1500 Monroe Street, 4th Fl, Fort Myers, FL 33901
PROJECT DETAILS:
SCOPE OF WORK: The North Lee County Reverse Osmosis Water Treatment Plant has an existing treatment capacity of 5.0 MGD permeate and is proposed to be expanded utilizing the Progressive Design-Build project delivery method. Substantial completion of this project is set for March 15, 2011.
The Purpose of the proposed project is to select one design-build team to work with Lee County Utilities to provide the following improvements to the existing North Lee County WTP: (1) evaluate and modify facility to achieve the original name plate production capacity of 5MGD permeate, (2) expand the facility from 5MGD permeate to 10 MGD permeate, (3) improve operability and maintainability of the facility. After selection, negotiations shall be entered to commence project execution, through progressive phasing.
CONTACT INFORMATION:
|
Name: Utilities |
Name: Mark D. Hrycyk | |
| Contact: Mikes Maillakakis | Phone: 239.533.8876 | |
| Phone: 239.533.8164 | Fax: 239.485.8335 |
DOCUMENT HOLDERS LIST:
| NAME | CITY, STATE | PHONE NUMBER |
| Cardinal Contractors, Inc. | Sarasota, FL |
941.377.8555 |
| BidNet, Inc. | Albany, NY |
800.677.1997 |
| Carollo Engineers | Saraosta, FL |
941.371.9832 |
| Malcolm Pirnie, Inc. | Fort Myers, FL |
239.274.1720 |
| CDM | Fort Myers, FL |
239.938.9600 |
| Reiss Engineering, Inc. | Orlando, FL |
407.679.5358 |
| Black & Veartch | Fort Myers, FL |
239.278.3830 |
| CH2M Hill | Naples, FL |
239.596.1715 |
| MWH | Cape Coral, FL |
239.573.5959 |
| Hydro Construction Company, Inc. | Fort Collins, CO |
970.225.2211 |
| HSA Engineers & Scientists | Fort Myers, FL |
239.936.4003 |
| Wright Construction Group | Fort Myers, FL |
239.481.5000 |
| CH2M Hill | Englewood, CO |
720.286.2431 |
| Cooner & Associates, Inc. - Surveying and Mapping | Fort Myers, FL |
239.277.0722 |
| Mitchell & Stark Const. Co., Inc. | Fort Myers, FL |
239.332.1632 |
| Mitchell & Stark Const. Co., Inc. | Naples, FL |
239.597.2165 |
| Tetra Tech, Inc. | Estero, FL |
239.390.1467 |
| LA Excavating | Newton, AL |
334.692.4392 |
| Source, Inc. | Cape Coral, FL |
239.549.2345 |
| Gora McGahey Architects | Fort Myers, FL |
239.275.0225 |
| IMS | San Diego, CA |
858.490.5018 |
| Harn R/O Systems, Inc. | Venice, FL |
941.488.9671 |
| Ecosystem Technologies, Inc. | Fort Myers, FL |
239.337.5310 |
| ETI | Fort Myers, FL |
239.337.5310 |
| Hydropro, Inc. | Riviera Beach, FL |
561.848.6788 |
| Gates Butz Institutional Construction, LLC | Naples, FL |
239.593.3777 |
| Tetra Tech | Orlando, FL |
407.839.3955 |
| Community Engineering Services, Inc. | Fort Myers, FL |
239.936.9777 |
| Hazen and Sawyer | Tampa, FL |
813.630.4498 |
| Poole & Kent Company of Florida | Miami, FL |
305.325.1930 |
| EMA, Inc. | Longwood, FL |
407.865.6601 |
| Haskell | Jacksonville, FL |
904.357.4285 |
| Stantec Consulting | Sarasota, FL |
941.365.5500 |
| MWH Constructors | Broomfield, CO |
303.410.4031 |
| Vogel Bros. Building Co. | Lakeland, FL |
863.646.5078 |
| BBL Florida | Estero, FL |
239.498.0777 |
| Onvia | Seattle, WA |
206.373.9500 |
| Encore Construction Company | Winter Garden, FL |
407.877.5903 |
| Hydropro, Inc. | Riviera Beach, FL |
561.848.6788 |
| TKW Consulting Engineers, Inc. | Fort Myers, FL |
239.278.1992 |
| Black & Veatch | West Palm Beach, FL |
561.420.5869 |
| DRMP, Inc. | Orlando, FL |
407.896.0594 |
| URS Corporation | Tampa, FL |
813.675.6504 |
| Forge Engineering, Inc. | Naples, FL |
239.514.4100 |
| Taylor-Pansing, Inc. | North Fort Myers, FL |
239.995.6669 |
| Johnson Engineering, Inc. | Fort Myers, FL |
239.334.0046 |
| GRAEF | Bonita Springs, FL |
239.495.4360 |
| Adams Robinson | Dayton, OH |
937.274.5318 |
| TSC Jacobs | Tampa, FL |
813.888.5556 |
| Membrane Systems, Inc. | Walnut, CA |
909.839.0355 |
| AECOM | Tampa, FL |
813.630.2500 |
| McKim & Creed, PA | Sarasota, FL |
941.379.3404 |
| Halcrow | Tampa, FL |
813.876.6800 |
| TLC Engineering for Architecture | Fort Myers, FL |
239.275.4240 |
| Brooks & Freund, LLC | Fort Myers, FL |
239.939.5251 |
| Parker/Mudgett/Smith Architects, Inc. | Fort Myers, FL |
239.332.1171 |
| Globaltech, Inc. | Boca Raton, FL |
561.997.6433 |
| Adams Robinson Enterprises, Inc. | Dayton, OH |
937.274.5318 |
| David Douglas Associates, Inc. | Fort Myers, FL |
239.337.3330 |
| Kraft Construction | Fort Myers, FL |
239.561.5181 |
| JJG | Norcross, GA |
678.576.6809 |
| Owen-Ames-Kimball Company | Fort Myers, FL |
239.561.4141 |
| Jones Edmunds & Associates, Inc. | Gainesville, FL |
352.377.5821 |
| Diversified Drilling Corporation | Tampa, FL |
813.988.1132 |
| Architecture, Inc. | Fort Myers, FL |
239.476.8888 |
| BCI Technologies | Fort Myers, FL |
239.433.9600 |
| AECOM | Jacksonville, FL |
904.279.7279 |
| Stouten & Associates Surveying & Mapping | Cape Coral, FL |
239.542.7499 |
| AM Electric of Venice, Inc. | Venice, FL |
941.488.6602 |
| AECOM | Chicago, IL |
312.373.7522 |
| WPC Industrial Contractors, LLC | Jacksonville, FL |
904.268.0099 |
| C.P.C. Concrete, Inc. | Cape Coral, FL |
239.574.9999 |
| Chris-Tel Construction | Fort Myers, FL |
239.226.0500 |
| AECOM | Orlando, FL |
407.425.1100 |
| Hole Montes, Inc. | Naples, FL |
239.254.2066 |
| Kimley-Horn and Associates, Inc. | Orlando, FL |
407.898.1511 |
| McCafferty Brinson Consulting, LLC | Plantation, FL |
954.802.3058 |
| Barraco and Associates, Inc. | Fort Myers, FL |
239.461.3170 |
| E.F. Gaines Surveying Services, Inc. | Fort Myers, FL |
239.418.0126 |
| Hazen and Sawyer, P.C. | Hollywood, FL |
954.967.7040 |
| MB McGowan & Associates | Novato, CA |
415.892.1080 |
| Automation Control Service, LLC | Pensacola, FL |
850.477.8440 |
| Doosan Hydro Technology | Tampa, FL |
813.482.3133 |
ADDENDA ISSUED:
Click on the Addenda Number below to download that Addendum.
|
ADDENDA # |
ISSUE DATE |
|
7/21/09 | |
|
| |
PROJECT SCHEDULE
|
EVENT |
LOCATION |
DATE |
TIME |
|
News Press Advertise |
|
7/3/2009 |
|
|
Plant Walk Thru |
18250 Durrance Rd, N Ft Myers |
7/15/2009 |
9:00 am |
|
Deadline Questions |
|
7/17/2009 |
5:00 pm |
|
Submittal Deadline |
Contracts Mgmt, 4th FL |
7/28/2009 |
2:00 pm |
|
Committee Review & Reference Checks |
|
7/29/2009 – 8/7/2009 |
|
|
Committee ShortList |
Public Works, 4th FL, Conf. 4D |
8/10/2009 |
2:00 pm |
|
Questions Issued to ShortList Firms |
By Contracts |
8/12/2009 |
|
|
Written Materials Due from Firms |
Contracts Mgmt, 4th FL |
8/25/2009 |
10:30am |
|
Presentations by Firms |
Public Works, 4th FL, Conf. 4D |
8/31/2009 |
1:00pm- 5:00pm |
|
Ranking Bluesheet in SIRE |
Contracts Management |
9/1/2009 |
|
|
Board approve ranking |
|
9/15/2009 |
|
|
Award & Contract to DB Firm |
Contracts Management |
9/16/2009 |
|
|
Contract Negotiations of Scope & Fees |
Utilities |
9/16/2009 – 9/23/2009 |
|
|
Phase I Award of Contract Bluesheet in SIRE |
Contracts Management |
9/25/2009 |
|
|
Board approval of Contract |
|
10/13/2009 |
|
|
Finalize contract execution by the Board |
Contracts Management |
10/13/2009 – 10/19/2009 |
|
|
Issue Notice to Proceed |
Contracts Management & Utilities |
10/20/2009 |
|
MINUTES OF MEETINGS:
(click to hear recording - please be patient as these are mp3 files and take a moment to load)
|
Final Selection |
|
CDM Constructors, Inc. |
CH2M Hill Engineers, Inc. |
|
Mitchell & Stark Construction Co., Inc. |
|