Lasted up-dated   11/17/2009

to view documents

 getacro.gif (712 bytes)

     
 

Proj. No.

Projects

Description

Manager
6002 12th Street W. – Sidewalk Gunnery to Sunshine Blvd. 07/21/09 – Construction Substantially Complete Sarah Clarke
4083 A & W Bulb Improvements   Rob Phelan
5034 Alico Rd. Connector Alignment Study. 11/17/09 – BOCC adopted the alignment late September 2009 Sarah Clarke
4030 Alico Rd. Ditch Right of Way 08/18/09 - Purchasing Right of Way Don DeBerry
4030 Alico Road 6-Laning 01/29/09 - Processing Resolution of necessity for specific properties. Buying ROW Don DeBerry
4030 Alico Rd. / Pennsylvania St. Connector & Signal 08/18/09 -Signal installed, design for Schwabb driveway under way Don DeBerry
6002 Arthur Sidewalk   Randy Cerchie
6047 Boca Grande Drainage.    04/15/08 - Construction completed. Eyra Cash
4044 Bonita Beach Road — Phase II. 11/16/09 – 100% plans complete, project ready for construction Eyra Cash
6002 Bonita Beach Road Sidewalk 09/16/08 - Construction completed. Eyra Cash
6002 Bonita Beach Road Sidewalk from Bonita Grande to I-75   Eyra Cash
4044 Bonita Beach Road – US 41 to Old US 41 Phase III.     11/16/09 – 60% plans complete working of the submittal to SFWMD. Eyra Cash
0700 Brantley Rd. – US 41 to Summerlin – canal barrier system. 11/17/09 – No change, Under Construction Sarah Clarke
4030 Briarcliff Canal Filter Marsh. 02/02/09 - Construction underway and nearly complete pending perimeter fencing and marsh plantings. Betsie Hiatt
6002 Buckingham Rd. Paved Shoulders. 11/17/09 – Bids opened, contract award on 11/17/09 BOCC agenda. Preconstruction meeting scheduled for 11/30/09. Construction to begin in December. Sarah Clarke
4088 Burnt Store Widening.    11/16/09 –No Change, (received 30% plans) SFWM permit application resubmitted August 4, 2009 - 30% ROW plans complete. Mike Rigsby
4020 Business 41 from Marianna to Littleton Rd.   Don DeBerry
5033 Cape Coral Parkway / Del Prado Turn Lane 04/21/09 - Project substantially complete.
Schedule punch list site visit.
 
Rob Phelan
5815 Cape Coral Toll   Paul Wingard
4683 Captiva Drive CCCL Permit. 02/02/09 – Dune restoration complete –monitoring and maintenance ongoing. Betsie Hiatt
6713 Coconut Road Widening West of US 41   Rob Phelan
0700 College Parkway Drainage   Sarah Clarke
4054 Colonial Blvd. from I-75 to SR 82, 4 Lane to 6 Lane.                 11/16/09 – Construction started Aug. 3.  Under Construction. Mike Rigsby
5054 Colonial Blvd. / McGregor to I - 75. 08/18/09 – No Change, Final IOAR submitted 7/10/09. Once FDOT/FHWA approve, the Project development summary report (PDSR) and Environmental Assessment (EA) will be submitted for review. Expect to hold public hearing late 2009. Sarah Clarke
6064 Colonial Blvd. / Metro Pkwy. Queue Jump. 11/17/09 – 60% plans on shelf Sarah Clarke
  Colonial initiative 04/15/08 –  Construction Completed Eyra Cash
4723 Corkscrew Road CRSA 08/18/09 - ongoing Don DeBerry
0700 Corkscrew Road Curve.    01/29/09 - Construction Completed. Eyra Cash
4078 CR 951 Extension. 08/18/09 - Draft EIS sent to Federal Highway. Voluntary right of way acquisition underway. Don DeBerry
4083 Cutlass Drive. 04/21/03/31/09 Rob Phelan
  Daniels Fire Station 7/15/08 – Permits finalized - 0.47 credits at Island Park Panther Fencing – complete, large female panther photographed in crossing Betsie Hiatt
TBD Daniel Parkway 4 Lane Widening. 04/21/09 - No change, Collecting available data on project Rob Phelan
6713 Daniels Pkwy. / Treeline Av. Dual Left-Turn Lane.   

09/16/07 –  Construction Completed.

Eyra Cash
6713 Daniels Pkwy & Bell Tower Dr. 11/16/09 –  Stimulus Project –   Out for bid.  Bids due 11/24               Lora Celec
6713 Del Prado / Cape Coral Pkwy Turn Lane 03/17/09 - Waiting for Mast Arm installation Rob Phelan
6742 Del Prado Blvd. Median Improvements. 11/16/09 – Construction Completed. Eyra Cash
5066 Duke Highway   Randy Cerchie
5067 Estero Blvd Phase 1      11/17/09 - Coordinating Meeting with Town, LeeDOT, LCU regarding Utility relocations Rob Phelan
  Estero Parkway Extension East of Ben Hill Griffin   Rob Phelan
5021 Estero River Flow Way Restoration 02/02/09 - Monitoring and maintenance ongoing. Betsie Hiatt
0700 Evans Connector – Metro Pkwy. to Evans Ave. 11/18/08 –  Draft report received and is under review. Sarah Clarke
4043 Gator Hole Preserve Tortoise Relocation. 02/02/09 – Initial land management for Phase 2 (80 acres) complete. Initiating contracts for FWC relocation site permit. Alico / Pennsylvania tortoise relocation complete. Betsie Hiatt
4060
4081
4083 Gladiolus Drive 4-Laning from Winkler to Pine Ridge Road including A&W Bulb Road and Bass Road Widening 11/17/09 – NTP 6-9-2008 – under construction.
• Traffic on north side lanes as of 8/17/09 – Contractor working on south side
• Working with Dave Douglas for A&W Bulb Road permit package
• Rev. 2, 3 & 4 issued
• Reviewing driveways on south side of roadway through Harlem Heights
Rob Phelan
6002 Glenwood Ave sidewalk (Ortiz to Prospect) & Tice St (Ortiz to Lexington) 09/16/08 – Construction Completed. Eyra Cash
4055 Gunnery Road      Under construction Nicole Maxey
6002 Gunnery Sidewalk – Lehigh HS to Buckingham Rd. 09/16/08 – Construction Completed Sarah Clarke
5721 Hancock Bridge Extension 08/18/09 – No Change, Analyzing engineering and economic data. Second public workshop to be held fall 2009. Sarah Clarke
4083 Hidden Lakes Mitigation Area. 02/02/09 – No change, Exotic Maintenance and monitoring ongoing. Betsie Hiatt
6713 Homestead & Milwaukee Turn Lane. 11/16/09,  (Westbound left turn lane on    Milwaukee Blvd.)  Stimulus Project – Construction complete.  Awaiting final inspection. Lora Celec
5063 Homestead Rd. – South of Sunrise to Alabama.    11/17/09 – SFWMD permit approved. Partial right-of-way acquisition underway with limited funds. Construction is not yet funded. Sarah Clarke
6713 Homestead Rd. & Beth Stacey Blvd. 03/18/08 -Construction of roadway and signal completed. Lora Celec
6002 Homestead Rd. Sidewalk.  08/18/09 – No Change Project has been submitted as a candidate for enhancement stimulus funding. Sarah Clarke
4723 Imperial Marsh Preserve Wetland and Panther Mitigation Area Corkscrew Mitigation. 02/02/09 – No change Exotic Maintenance and monitoring ongoing. Betsie Hiatt
4060 Imperial Street 4-Laning from Bonita Beach Road to E. Terry Street Under Construction Nicole Maxey
8546 Island Park Addition 02/02/09 –  Purchase Contract denied
Wake / Hatchee – in permitting.
Betsie Hiatt
8546 Island Park Regional Mitigation Project (North and South).    02/02/09 - No change – (North and South)- North Phase Completed. South Phase Complete. Monitoring and maintenance ongoing. Betsie Hiatt
6674 Joel Blvd. at Country Club - Left turn lane. 11/17/09 – Construction underway; delayed pending relocation of a FGUA waterline. Sarah Clarke
6713 Lee Blvd. & Leonard Blvd. 04/15/09 – U-Turn location shown on Concept Plans from Traffic at Driveway location of proposed City of Fort Myers development. Recommend not progressing this project. Rob Phelan
6713 Lee Blvd. / Sunshine Blvd. Turn Lanes.  11/16/09 - Pre construction meeting 11/30/09
 
Eyra Cash
6713 Leland Heights Blvd. / Lee Blvd. 11/17/09 – Preparing preliminary design for minor intersection improvements Rob Phelan
0700 Littleton Extension. 04/15/08 – Project completed. Sarah Clarke
6002 Littleton Sidewalk—Old 41 to US 41. 11/16/09 –  100% plans Complete, funds available for construction BPAC, getting ready to advertise. Eyra Cash
5060 Luckett / Sunshine Blvd. Corridor Extension Studies. 11/17/09 – No Change, Final report complete. Sarah Clarke
5714 Master Bridge   Ehab Guirguis
5904 Matlacha Bridge Replacement. 08/18/09 - to be advertised 8/28/2009 Don DeBerry
0700 N. Airport Rd. Extension. 11/17/09 – Discussion with developer have resumed. Agreement is under review. Sarah Clarke
4007 Orchid Isles ROMA. 02/02/09 - No change, Evaluation phase. Betsie Hiatt
  Oriole Road.  03/16/09 - No change -  DOS2008-00010, equivalent to 60 percent plans, is under review. Andy Getch
4072 Ortiz Avenue 4-Laning from SR 82 to SR 80 (Luckett Road).   11/16/09 – SFWMD permit approved, & working on 100% plans Eyra Cash
4007 Panther Fencing. 7/15/08 – No change - Completed. Large female panther photographed in crossing. Betsie Hiatt
4007 Panther Mitigation Area (Sec. 33). 02/02/09 –  Incorporated in to Colonial Widening permit application. Betsie Hiatt
5722 Persimmon Ridge Bridge   Don DeBerry
4007 Pine Ridge Facility. 02/02/09 – No change - in permitting / 2.13 mitigation credits will be provided at Island Park Betsie Hiatt
4065 Plantation Extension from Idlewild to Colonial Blvd.      11/16/09 - Construction Complete
Opened Nov. 13
Mike Rigsby
TBD Pondella Medians. 11/17/09 – Looking at median locations for Pondella Road. Rob Phelan
6024 Roadway Beautification Projects   Pat Moore
4084 Sandy Lane Design. 06/12/09 Corridor Evaluation Study complete by Cella & Associates and adopted by BoCC in November 2004. Project is on hold pending funding.

Andy Getch

4084 Sandy Lane Extension 03/16/09 - No change - Project is not funded in the current CIP Andy Getch
  Sanibel Causeway 02/02/09 - Drafting permit applications for permit modification / mitigation requirement. Betsie Hiatt
TBD Sanibel Causeway U-Turn 04/21/09 - • U-turn east of Toll Plaza incorporated into TYLin Plans to be included in Stimulus plans at Toll Plaza. Rob Phelan
4604 Six Mile Cypress Parkway 11/17/09 - • ARRA Stimulus Project
• Public Hearing held 11/10/09
• Awaiting review comments on Plans Submitted to FDOT on 11/5/09
• Working on DO package
Rob Phelan
6002 Six Mile Cypress Pathway – Daniels to Metro Pkwy.     07/21/09 – Construction Complete Sarah Clarke
6002 Six Mile Cypress Pathway – Metro to US 41. 07/21/09 – Construction Complete Sarah Clarke
6713 Six Mile Cypress Pkwy. & Independence Circle W. 08/18/09 –  Construction is complete. Lora Celec
6002 Slater Rd. – sidewalk Bayshore to Del Prado Blvd. 11/17/09 –No Change,  Under Construction Sarah Clarke
5064 SR 82 / Daniels Dual Left-Turn Lane. 05/19/09 –  Construction Completed. Eyra Cash
6002 Stringfellow Rd.  Sidewalk – 1st Ave. to York Rd. 11/16/09 – Requested survey, design in house ~ project on hold due to funding Eyra Cash
6007 Summerlin Rd. – Cypress Lake to
Boy Scout Drive.     
11/17/09 – No Change, Under construction. Sarah Clarke

4067

 
Summerlin Road Sidewalk  from
San Carlos Blvd. to Gladiolus Dr.
11/16/09 - Summerlin Road Sidewalk—90% complete, in review.
 
Mike Rigsby
4067 Summerlin Road Sidewalk from Lakewood to Gladiolus Dr. 11/16/09 – Construction Complete Eyra Cash
4604 Sunniland Blvd – Lee Blvd to Park St. 11/17/09 - Updating Plans for potential ARRA Stimulus Funding. Rob Phelan
6713 Sunshine Blvd. & 12th St. West 11/17/09 - Under Construction. Rob Phelan
6002 Texas Rd. – sidewalk Leeland Hgts. To Davis. 07/21/09 – Construction Completed. Sarah Clarke
4053 Three Oaks North from Alico to Airport Ditch (Source, Inc.).    02/02/09 - Consultant working on the SFWMD & USACOE RAI. Project is under construction. Andy Getch
  Three Oaks Park Rehab. 08/18/09 - Under Construction. Don DeBerry
4053 Three Oaks Parkway From
Alico Canal to Daniels Parkway
11/16/09 – Consultant received additional RAI from SFWMD & waiting on ACOE RAI. 90% plans complete. Eyra Cash
4043 Three Oaks Parkway South from Brooks to E. Terry Street   Under Construction. Nicole Maxey
4081 Three Oaks Parkway Widening from Corkscrew to Alico Rd.     Under Construction. Nicole Maxey
4081/
5021
Three Oaks Widening and Estero Pkwy Wetland Mitigation Under Construction. Betsie Hiatt
6002 Tice St. – sidewalk Ortiz to Lexington.  04/15/08 –  No change – construction nearing completion. Sarah Clarke
6002 Tice St. – sidewalk Waverly to Ortiz. 04/15/08 – Record plans received. Project Completed. Sarah Clarke
  Treeline Ave 02/02/09 - Drafting Technical assistance letter for panther signs and speed limits. Betsie Hiatt
TBD Veteran’s Pkwy. merge lane at Santa Barbara 04/21/09 • Provided sketch, estimate and issues with merge lane to Scott. It is to be discussed at COCC TAC meeting 1/29/09. Rob Phelan
5020 Veteran's Pkwy. Mitigation Area. 02/02/09 – Deed to state DEP pending with County Lands. Coordinating additional exotic removal. Betsie Hiatt
5029 Veteran's Ramp. 04/15/08 – Substantially complete. Sarah Clarke
  Veteran's / Surfside Intersection   Don DeBerry
4007 Wake / Hatchee 7/15/08 – No change - In permitting. Betsie Hiatt
4007 Wild Turkey Strand Wetlands and Panther Mitigation Area 02/02/09 –  In permitting. Drafting ditch crossing permit applications for P&R. Betsie Hiatt
6675 Williams Rd. at 5th St. – left turn lane. 11/17/09 – No Change, Under Construction. Sarah Clarke
6002 Williams Road Sidewalk.    05/19/09 –  Construction Completed. Eyra Cash
       
 
Elderberry Lane. 08/18/09 - Road open Mike Rigsby
MSBU – Western Acres, Harbor Dr., Homestead Ln., San Carlos Dr. 11/17/09 – Bids received, contract awarded. Notice to proceed issued 11/9/09. Sarah Clarke
Roundabouts on Sunshine & 23rd . 08/18/09 - Under Construction Don DeBerry
Advertise:
951 / Golf Course Maintenance Swap 01/29/09 - Ranking approved by BoCC 4/15/2008 will begin negotiating contracts. Don DeBerry
Orange River Paved Shoulders Don DeBerry
Palmetto Ridge Bridge Replacement  01/29/09 - Selected consultants. Don DeBerry