|
|
|
November 12, through November 18, 2009 |
|
|
|
|
 |
Bonita Beach Road - Road Widening
Project East of Bonita Grade Drive -The week of
February 2, 2009, construction activities began on the
widening of Bonita Beach Road east of Bonita Grande
Drive. Construction activities are expected to take 6-9
months to complete. Proposed work includes the widening of
approximately two miles of Bonita Beach Road from two
lanes to four lanes. Work will also include rebuilding
portions of the existing two lanes, installation of drainage
and relocation of a forcemain. Two travel lanes will be
maintained in order not to disrupt the flow of traffic in the
area. |
 |
Ongoing work on Bonita Beach Road –
Construction is ongoing for the widening of Bonita Beach
Road east of Bonita Grande. The contractor is
planning on switching traffic onto the newly constructed
southerly lanes in front of Worthington Community the week of
November 9th. This switch is necessary so that the existing
roadway in front of the Worthington Community can be
demolished and rebuilt.
The lane switch is tentatively scheduled for Wednesday
November 11th. As part of the traffic switch, some lane
closures with flagmen are planned for Wednesday, November
11th. When the traffic switch occurs, both eastbound and
westbound traffic will travel on the newly constructed
southerly lanes of Bonita Beach Rd. Please use caution when
traveling this section of Bonita Beach road as traffic flow
patterns will be changing.
If you have any questions,
please
contact Eyra Cash at
533-8562 |
 |
Colonial Blvd. at
Plantation Rd. Extension (Veronica Shoemaker Blvd) – Turn
lane improvements to this intersection started on Monday
July 6, 2009. Please use caution when approaching this
intersection as men and equipment will be working in close
proximity to the edge of the road along with intermittent lane
closures. The tentative completion date is end of November, 2009.
If you have any questions,
please
contact Mike Rigsby at
(239)
533-8513.. |
 |
Colonial Blvd (CR
884) Six Laning from I-75 to State Rd 82 (approx. 2.7
miles in length)
Construction activities began on Monday, August 3, 2009.
Proposed work consists of widening an existing four lane
highway facility, to a six lane urbanized divided highway.
This will include the installation of street lighting,
signalization, bridge widening and utility modifications. Two
8 foot wide asphalt multi-use sidewalks along the north and
south sides of the road will be added.
The tentative completion
date is April, 2011.
Utility work will be ongoing around Treeline Avenue on
both the north and south side of Colonial Blvd. for the
next several weeks relocating utilities. Traffic on
Colonial Country Club Blvd. will be detoured to one side
of this divided road at the Colonial Blvd. Intersection for
utility work this week. Work will be ongoing under the I-75
Bridges along Colonial Blvd. Construction Traffic is
heavy, so please drive through the area with caution.
If you have any questions, please contact Eyra Cash at (239) 533-8562 |
 |
Gladiolus Drive Widening from Pine Ridge Road to Winkler Road
– Construction activities are continuing on Gladiolus Drive
and on Bass Road to widen Gladiolus Drive from 2
lanes to 6 lanes from Winker Road to Bass Road and to 4
lanes from Bass Road to Pine Ridge Road and to widen
Bass Road from 2 lanes to 4 lanes from Health Park to
Gladiolus Drive. Motorists are advised that a lane
reduction is in place on the westbound approach of
Gladiolus Drive to Winker Road. Construction
activities are currently occurring through out the corridor.
Lane closures may occur and will typically be at night time
between 7:00 pm and 6:00 am with some work occurring off the
roadway during the day. The tentative completion date is
Fall, 2010.
Beginning Monday,
November 9, 2009 Hagie Drive will be closed to traffic
from Gladiolus Drive south to Forest Knoll Court
as part of the Gladiolus Drive Widening project. This
closure is necessary to complete underground utility work,
pour curb and pave the intersection. Traffic may use Concourse
Drive to Duera Mae to access Hagie Drive south
of Forest Knoll Court. This closure is expected to last
through mid-December.
If you have any questions,
please contact Robert Phelan at
(239)
533-8594. |
 |
Construction on
Gunnery Road from SR 82 to Lee Blvd began February 27th
and will last 16 months. This project will cause traffic
delays. Please use an alternate route.
If you have any questions,
please contact
Randy Cerchie at (239) 533-8580. |
 |
Summerlin Rd. from Cypress Lake Dr.
to Boyscout Rd. – work continues on widening the
Southbound roadway from north of college to Cypress Lake
and on the northbound roadway near Boyscout Rd.
Work is underway on the bridge piers and the retaining walls
on the overpass at College Pkwy. The dual left turn
lanes on College Pkwy have been reduced to single lefts
for this phase of the project to allow for the scaffolding to
construct the overpass. The tentative completion date on this
project is Summer of 2010.
If you have any questions,
please contact Sarah Clarke at
(239) 533-8718. |
 |
Sunshine Blvd at
12th St W – Intersection improvement construction is
underway at this intersection. Turn lanes are being added to
improve the intersection. Motorists are advised that temporary
lane closures may be necessary, and delays are possible. The
work is expected to be completed by late December.
If you have any questions please
contact Michael Tisch at 533-8110 |
|
Road / Bridge Maintenance: |
 |
Buckingham - Lee County DOT Operations will be
managing the overlay project for Bridge # 124026 on Orange River
BLVD. This project is scheduled to be completed on Thursday, May
8th.There will be lane closures.
If you have any questions, please contact Ehab
Guirguis at (239) 533-9400. |
 |
Del Prado Blvd. – We will be performing bridge
maintenance on the bridge north of Coronado Pkwy. on
Del Prado Blvd.. This will be night work starting Oct. 29th
until Dec. 3rd on Thursday nights, with lane
closures starting at 7:00 pm until 3:30 am.
If you have any questions please contact Doug Busbee at
533-9429. |
 |
Lee County DOT Operations will be managing the
pipe lining in the following locations:
1- Eaglesmere Dr. on 4/13/20009
2- E. Jasmine Rd. @ Clayton Ave. on 4/14/2009.
3- Oriole Rd. @ Cypress Dr. South on 4/15/2009
There will be lane closures,
If you have any questions, please contact Ehab Guirguis at
(239) 533-9400 |
 |
Moody Road Bridge- Lee County DOT Operations
will be managing the overlay project for Bridge # 124103 on Moody
Road. This project is scheduled to be completed by September
6th. There will be lane closures.
If you have any questions,
please contact Ehab Guirguis at
(239) 533-9400. |
|
Landscaping: |
 |
Summerlin Road –
Landscaping – Lee County DOT Operations will be managing the
installation of irrigation and landscaping along Summerlin Road,
between Sanibel Island and Gladiolus Drive. This
project is scheduled to be completed by the end of November 2009.
Lane closures and traffic impacts may occur.
If you have any questions please contact Bob DeBrock at
(239) 533-9425. |
|
Traffic
Signal Work:
|
|
|
No updates at this time. |
|
County-Wide Road Resurfacing: |
 |
Resurfacing various streets countywide began May 5, 2009 and will
last for 12 months. |
|
County-Wide
Sidewalks Construction: |
|
|
Brantley Rd.
will be closed to through traffic overnight Monday, November
16, 2009 to make repairs to a pipe crossing under Brantley
Road. A pipe crossing under Brantley Road has
deteriorated and must be replaced. The work can be
accomplished in one overnight period rather
than over a period of
several days with one lane traffic for the duration.
The road will be closed at the pipe crossing location between
Forest Wood East/New Brittany Blvd. and Forrest Wood
West/World Plaza Lane. The closure will from 6:30 pm
Monday 11/16/2009 to 6:00 am Tuesday 11/17/2009.
Traffic can approach Forrest Wood West/New Brittany from
Summerlin Rd. or Forrest Wood East/World Plaza Lane
from US 41 but will not be able to cross through the
work area. |
 |
Brantley Rd. – Barrier and Sidewalk Project
- Work is continuing to install a guardrail along the
south side of Brantley Rd. from US 41 to
Summerlin Rd. Two culverts that are deteriorating will be
replaced and a sidewalk constructed where gaps exist on the
north side of Brantley Rd. Traffic will be maintained
but may be reduced to one lane intermittently to install the
culverts and guardrail. The project is expected to be complete
this Fall.
If you have any questions,
please contact Sarah Clarke at (239) 533-8718.
|
 |
Slater Road Sidewalk – Lee County DOT is
constructing a 5’ sidewalk along the east side of Slater
Road from Bayshore Road to Mellow Lane. The
project began on Monday, April 27, 2009, and is scheduled to
be completed in November, 2009.
If you have any questions,
please contact Sarah Clarke at
(239) 533-8718. |