|
|
|
February 4, through February 10, 2010 |
|
|
|
|
 |
Bonita Beach Road - Road Widening
Project East of Bonita Grade Drive -The week of
February 2, 2009, construction activities began on the
widening of Bonita Beach Road east of Bonita Grande
Drive. Construction activities are expected to last until
March 2010. Proposed work includes the widening of
approximately two miles of Bonita Beach Road from two
lanes to four lanes. Work will also include rebuilding
portions of the existing two lanes, installation of drainage
and relocation of a forcemain. Two travel lanes will be
maintained in order not to disrupt the flow of traffic in the
area.
If you have any questions,
please
contact Eyra Cash at
533-8562 |
 |
Buckingham Road
Paved Shoulders from SR82 to Neal Road -Work will begin
February 8, 2010 to add 4 wide paved shoulders on
Buckingham Rd. This work will require one lane to be
closed during much of the work effort. Lane closures will be
limited to off peak hours, after 9 a.m. and before 3 p.m.;
however an alternate route is suggested. Work is expected to
be complete by April 1, 2010. |
 |
Colonial Blvd (CR
884) Six Laning from I-75 to State Rd 82 (approx. 2.7
miles in length)
Construction activities began on Monday, August 3, 2009.
Proposed work consists of widening an existing four lane
highway facility, to a six lane urbanized divided highway.
This will include the installation of street lighting,
signalization, bridge widening and utility modifications. Two
8 foot wide asphalt multi-use sidewalks along the north and
south sides of the road will be added.
The tentative completion
date is April, 2011.
Colonial Blvd - Utility work will be ongoing around
Treeline Avenue on both the north and south side of
Colonial Blvd. for the next several weeks for relocation
of utilities. Work will be ongoing under the I-75 Bridges
along Colonial Blvd. Construction Traffic is heavy, so
please drive through the area with caution.
If you have any questions, please contact Eyra Cash at (239) 533-8562 |
 |
Florence Ave & State Rte 80 Shandlers Community Park
Entrance at SR 80 (Palm Beach Blvd.) and Florence
Ave. On February 2, 2010, construction activities
anticipated to take 2 weeks will begin. The proposed work will
remove the SR 80/Florence Ave. entrance. Access to the park
can be obtained from Royal Palm Park Rd.
If you have any questions, please contact Eyra Cash at (239) 533-8562 |
|
 |
Gladiolus Drive Widening from Pine Ridge Road to Winkler Road
Construction activities are continuing on Gladiolus Drive
and on Bass Road to widen Gladiolus Drive from 2
lanes to 6 lanes from Winker Road to Bass Road and to 4
lanes from Bass Road to Pine Ridge Road and to widen
Bass Road from 2 lanes to 4 lanes from Health Park to
Gladiolus Drive. Motorists are advised that a lane
reduction is in place on the westbound approach of
Gladiolus Drive to Winker Road. Construction activities
are currently occurring through out the corridor. Gladiolus
Dr. -Lane closures may occur and will typically be
at night time between 7:00 pm and 6:00 am with some work
occurring off the roadway during the day. The tentative
completion date is Fall, 2010.
If you have any questions,
please contact Robert Phelan at
(239)
533-8594.
Beginning at 7 p.m.,
Wednesday, February 3nd and Thursday, February 4th
construction crews will pave the intersection at Gladiolus
Drive and Winkler Road. Law enforcement will be
present to direct traffic during intermittent lane closures.
The work is expected to be complete by 6 a.m.
On Thursday, February 4th and Friday, February 5th from 7 p.m.
to 6 a.m. construction crews anticipate placing the final lift
of asphalt on Bass Road south of Gladiolus Drive
to Health Park. Expect intermittent lane closures. The
work is expected to be complete by 6 a.m. However, if delayed
due to weather or additional work is required; crews will
complete the paving on Sunday, February 7th, between 7 p.m. to
6 a.m. Flagmen will be on site to direct
traffic.
The
Contractor is anticipating activation of the signal at A&W
Bulb Road and Gladiolus Drive the week of February
15th, the signal will operate in flash mode prior being placed
into full operation. In the event of delays the activation of
the signal may be postponed until the week of February 22nd. |
 |
Construction on
Gunnery Road from SR 82 to Lee Blvd began February 27th
and will last 16 months. This project will cause traffic
delays. Please use an alternate route.
If you have any questions,
please contact
Randy Cerchie at (239) 533-8580. |
 |
Lee Blvd/ Sunshine Blvd. -Intersection
of Lee Boulevard/Sunshine Boulevard On February 20,
2010, construction activities anticipated to take 5 months to
complete will begin. The proposed work will extend along
Sunshine Boulevard approximately 1000 each direction from
Lee Boulevard; and includes the addition of a left turn
lane and traffic signal modifications.
If you have any questions, please contact Eyra Cash at (239) 533-8562 |
 |
Sanibel Toll Plaza Bicycle/Pedestrian Improvements - Work
will begin February 8, 2010 to add paved shoulders/construct a
bike path through the toll booth area. McGregor Blvd.
will be resurfaced through the limits of the work area and
additional boat trailer parking will be added for the boat
ramp. All through travel lanes will remain open during day
light hours; activities requiring lane closures (resurfacing)
will be done at night. Work is expected to be complete by
April 30, 2010. |
 |
Summerlin Rd. from Cypress Lake Dr.
to Boyscout Rd. work continues on widening the
Southbound roadway from north of college to Cypress Lake
and on the northbound roadway near Boy Scout Rd. Work
on the retaining wall on the south side has been suspended due
to the presence of asbestos and will resume once a
determination of the amount and disposable method has been
approved. Work on the retaining wall on the north side of the
intersection will begin the week of Jan. 11th.
The dual left turn lanes on College Pkwy. completion
date is summer of 2010.
If you have any questions,
please contact Sarah Clarke at (239) 533-8718.
|
|
Road / Bridge Maintenance: |
 |
Buckingham - Lee County DOT Operations will be
managing the overlay project for Bridge # 124026 on Orange River
BLVD. This project is scheduled to be completed on Thursday, May
8th.There will be lane closures.
If you have any questions, please contact Ehab
Guirguis at (239) 533-9400. |
 |
Del Prado Blvd. We will be performing bridge
maintenance on the bridge north of Coronado Pkwy. on
Del Prado Blvd.. This will be night work starting Oct. 29th
until the end of January, 2010 . on Thursday nights, with lane
closures starting at 7:00 pm until 3:30 am.
If you have any questions please contact Doug Busbee at
533-9429. |
 |
Lee County DOT Operations will be managing the
pipe lining in the following locations:
1- Eaglesmere Dr. on 4/13/20009
2- E. Jasmine Rd. @ Clayton Ave. on 4/14/2009.
3- Oriole Rd. @ Cypress Dr. South on 4/15/2009
There will be lane closures,
If you have any questions, please contact Ehab Guirguis at (239) 533-9400 |
 |
Moody Road Bridge- Lee County DOT Operations
will be managing the overlay project for Bridge # 124103 on Moody
Road. This project is scheduled to be completed by September
6th. There will be lane closures.
If you have any questions,
please contact Ehab Guirguis at (239) 533-9400. |
|
Landscaping: |
 |
Summerlin Road
Landscaping Lee County DOT Operations will be managing the
installation of irrigation and landscaping along Summerlin Road,
between Sanibel Island and Gladiolus Drive. This
project is scheduled to be completed in late March 2010.
Lane closures and traffic impacts may occur.
If you have any questions please contact Bob DeBrock at
(239) 533-9425. |
|
Traffic
Signal Work:
|
 |
SR 80 & Ortiz Ave - Beginning 1/19/10 Major Signal
repairs to begin at SR 80 & Ortiz. The work is planned
maintenance in conjunction with road work.
Expect delays until March 1st. |
 |
Traffic Signal repairs will be done at the following
intersections from 9:00 am to 3:00 pm:
2/9/10 - Cape Coral Pkwy & Vincennes
2/10/10 - Cape Coral Pkwy & Nicholas
2/11/10 - Cultural Club & Nicholas
Cape Coral Police Department will be onsite
all 3 days to direct traffic |
|
|
If you have any signal work questions please contact
Tom Watts @ 533-9541. |
|
County-Wide Road Resurfacing: |
 |
Resurfacing various streets countywide began May 5, 2009 and will
last for 12 months. |
|
County-Wide
Sidewalks Construction: |
|
|
No
updates at this time. |